# Original Bopbun example code and synthetic input: CC0-1.0.
# Python 3.12.4, NumPy 1.26.4, Matplotlib 3.8.4. See LICENSE.txt for font rights.
from pathlib import Path
import csv,json,math,itertools
import numpy as np
import matplotlib
matplotlib.use('Agg')
import matplotlib.pyplot as plt
from matplotlib import colors,patches
OUT=Path(__file__).resolve().parent
plt.rcdefaults()
plt.rcParams.update({'font.family':'DejaVu Sans','font.size':11,'figure.dpi':120,'savefig.dpi':160,'pdf.fonttype':42})
def pair():
    f0,a0=plt.subplots(figsize=(7.2,4.5),layout='constrained')
    f1,a1=plt.subplots(figsize=(7.2,4.5),layout='constrained')
    return f0,a0,f1,a1
def data_file(names,rows):
    with (OUT/'data.csv').open('w',newline='',encoding='utf-8') as f:
        w=csv.writer(f);w.writerow(names);w.writerows(rows)
before,a0,after,ax=pair()
dur=np.array([2.,3,4,1]);pred=[[],[0],[0],[1,2]];finish=[]
for i in range(4):finish.append(dur[i]+max([finish[j] for j in pred[i]] or [0]))
start=np.array(finish)-dur;a0.bar(range(4),dur);a0.set(xlabel='Task',ylabel='Duration',title='Task durations alone omit precedence')
ax.barh(range(4),dur,left=start);ax.set(yticks=range(4),xlabel='Time',ylabel='Task',title='Earliest starts under the diamond precedence');data_file(['task','duration','start','finish'],zip(range(4),dur,start,finish));metric=finish[-1]

before.savefig(OUT/'before.png')
after.savefig(OUT/'after.png')
after.savefig(OUT/'after.pdf',metadata={'CreationDate':None,'ModDate':None})
after.canvas.draw()
print(json.dumps({'metric':float(metric),'axes':len(after.axes),'inputRows':sum(1 for _ in (OUT/'data.csv').open())-1}))
plt.close('all')